A Free-Market Energy Blog

Massachusetts Offshore Wind Troubles

By -- April 5, 2023

“With two of the three projects in trouble, Massachusetts will not meet its clean energy goals, and when they do, the power prices will be higher than expected…. The energy chaos in the state is getting interesting with significant implications for the offshore wind business.”

The ongoing saga of Commonwealth Wind’s future took another twist in late January when it filed with the Massachusetts Supreme Court a petition to set aside the order by the Massachusetts Department of Public Utilities (PUC) issued on December 30, 2022, approving the Power Purchase Agreement (PPA) prices negotiated with the three local utilities purchasing the electricity.

The challenging, worsening economics have upset the future of the project. Avangrid, the developer of the Commonwealth Wind project, wishes to renegotiate the PPA prices or to have them rejected by the PUC which would then allow Avangrid to rebid the project’s output in the next Massachusetts wind power solicitation scheduled for this spring.

The saga commenced in the early fall when Avangrid told investors and analysts that it was going to request a “price adjustment” to its PPAs that would improve the project’s economics. Avangrid officials sought to reopen negotiations over the price of its electricity, which would enable the project to be financed.

Management currently calls the wind farm “unfinanceable” because “unexpectedly high and persistent inflation, supply shortage and increases in supply costs, the Russian invasion of Ukraine, and rapid increases in interest rates had negatively affected the economics of the Project to the point where the PPAs would no longer facilitate the financing of the Project due to the Project’s negative net present value.”

Before Avangrid filed of its petition, Climatewire authored an article about the risk to Massachusetts’ clean energy mandate from the travails of one company – Avangrid. The company has won three of the five major clean energy projects awarded by the state since 2017. The three projects include Mayflower Wind I, Commonwealth Wind, and New England Clean Energy Connect, a transmission line through Maine bringing hydropower from dams in Quebec that would supply 18% of Massachusetts power. The transmission project is mired down in legal battles, while Commonwealth Wind cannot be built because Avangrid cannot raise the money needed, according to its recent filings.

Mayflower Wind is currently under construction and should be completed by late this year. The bigger issue is how these projects would impact the state’s clean energy goal. The state needs to reduce its CO2 levels from around 64 million tons in 2020 to about 47 million tons by 2030. Avangrid estimates its three projects would contribute a combined seven million tons in annual emissions reductions or about 40% of the reductions needed by Massachusetts.

With two of the three projects in trouble, Massachusetts will not meet its clean energy goals, and when they do, the power prices will be higher than expected.

Climatewire pointed out that the original clean energy law mandated that, at each offshore wind solicitation, the prices negotiated needed to be lower than those agreed to in the most recent solicitation. This irrational policy assumed that the downward trajectory of renewable energy prices would continue.

Rising Wind Costs

That downward trend has not only stopped but prices have likely backtracked by five years or more. The policy has been changed in the recently amended legislation. The article pointed out that the Commonwealth Wind price was much more aggressive in producing a lower power price. Therefore, the magazine wonders whether merely giving Avangrid back the $5 per MWh bid undercut might be sufficient to resolve the standoff.

Where does the Avangrid petition go? Our reading of the order and the petition leaves us wondering about the timeline of the original order. The PUC asked if Avangrid was going to appeal their rejection of the company’s request to delay the PPA review.

The company said no–but then filed a challenge 32 days later. Avangrid is claiming in its petition that the PUC did not accept additional Avangrid data pertinent to the matter before issuing its order. But the company said it was not going to appeal, at which point the PUC closed the file and began deliberation before rendering its order.

The bigger problem facing the court, other than judging the facts, is the precedent a ruling in favor of Avangrid would set for other offshore wind projects and their developers. It could unleash a rush of developers wanting to renegotiate their PPAs to get higher prices. The energy chaos in Massachusetts is getting interesting with significant implications for the offshore wind business.

5 Comments


  1. John W. Garrett  

    The sooner these charlatans come to grief, the better (as long as the clusterf*cks occur in the People’s Sovereign Socialist Republics of Massachusetts, New York, California or the formerly Great Britain or Germany).

    I cannot wait for THEIR lights to go out and for THEM to find out (the hard way) that cold kills.

    Reply

  2. Clayton Dan McKay  

    Crush Offshore Wind and the Whole New England Commie Renewable Program Collapses

    Reply

  3. Van Snyder  

    What does $5 per Megawatt mean? Energy is usually sold by the megawatt-hour (or kilowatt hour). If it was supposed to be megawatt-hour, then the price is ridiculously low. That wouldn’t cover operations and maintenance, let alone capital amortization.

    Reply

  4. Barbara Durkin  

    “OW North America is a 50 percent owner of Mayflower Wind,”

    “EDP Renewables and ENGIE have combined their existing and planned offshore wind efforts to form a new company, Ocean Winds (OW),”
    https://www.engie-na.com/oceanwinds/

    !!! THIS IS CHINA-
    ‘Wind energy: Ocean Winds sets sail to conquer the West’
    https://www.engie.com/en/ocean-winds-wind-energy

    EDP’s main shareholder is China Three Gorges (CTG).
    https://www.edp.com/en/investors/shareholder-structure

    ‘China Clean Energy Syndicate’
    [2020 Aug 31]
    “The Pentagon enlists 11 Chinese companies in the “PLA-Controlled” entity list: the new members include China Three Gorges “
    https://energyiceberg.com/china-clean-energy-syndicate-2020-aug-31/

    9/21/20
    ‘China Three Gorges (CTG) is EDP’s largest shareholder with a 21.55% stake and has been on the US government’s so-called “blacklist” since 28 August. This list, published and regularly updated by the US Ministry of Defence, includes dozens of companies that are considered “Chinese communist military companies”. The American market, it should be noted, is the most important for EDP, through EDP Renováveis”
    https://econews.pt/2020/09/21/edps-chinese-shareholder-joins-the-us-blacklist/

    2020/07/06
    ‘Portuguese judge suspends EDP boss in corruption probe, CFO named interim head’
    https://www.reuters.com/article/us-edp-ceo-investigation-idUSKBN2471R9

    2021/07/25
    “The Public Prosecutor’s Office argues that EDP and the French company Engie “prepared, planned and built an ingenious legal construction” through successive creations and mergers of companies with “the sole purpose of not paying the State the taxes that would be due to it,” according to the Lisbon Court of Appeal’s ruling.”
    https://econews.pt/2022/07/25/edp-and-engie-suspected-of-tax-evasion-in-sale-of-douro-dams/

    Ocean Winds = EDP & ENGIE
    2021/07/26
    “French utilities giant Engie has been hit with penalties of more than $2.5 million after door-to-door sales agents allegedly fraudulently switched hundreds of power and gas customers to its Australian retailing business without consent.
    The penalties against the Engie-owned retailer Simply Energy, announced on Monday, are the biggest ever imposed by Victoria’s Essential Services Commission.”
    https://www.smh.com.au/business/companies/hundreds-of-power-and-gas-customers-caught-in-sophisticated-fraud-20210726-p58cyn.html

    “ENGIE”
    ‘Paradise Papers: How Engie pulled $1 billion from Australian power plant ahead of carbon tax’
    https://www.abc.net.au/news/2017-11-09/engie-pulls-money-out-of-australian-loy-yang-b-power-station/9130602

    Ocean Winds holds several U.S. offshore wind leases, MA, NY, NJ, CA.

    Emphasis added. Offshore Wind is China’s Stalking Horse

    ‘Wind energy: Ocean Winds sets sail to conquer the West’
    https://www.engie.com/en/ocean-winds-wind-energy

    Thank You,
    Barbara Durkin

    Reply

Leave a Reply