A Free-Market Energy Blog

Economics and Performance – The Primary Deficiencies of Wind Power

By Jerry Graf -- June 17, 2010

[Editor’s note: Mr. Graf’s cash flow analysis of wind power projects is presented as another view of the inappropriateness of planned public policy in the electricity sector. The economics of wind power is a broad topic; previous posts at MasterResource are listed at the end of this post. For general problems of industrial wind, see here.]

There are many arguments to be made against government subsidization of industrial wind power, some objective and others subjective. We hear about noise, shadow flicker, disruption of wildlife, lack of consistent energy output (intermittency), questionable performance with respect to pollution reduction, and undesirable aesthetic appearance.

It occurs to me, however, with regard to subsidies for energy ventures and technology, three things must be kept in mind:

(1) any good investment must be made in worthwhile ventures that can show a reasonable return;

(2) arbitrarily subsidizing some ventures may cause inadvertent (or advertent) exclusion of others; and

(3) jobs cannot be created by subsidizing ventures that do not provide a viable return. We must keep our eye on the economic ball, and structure our primary arguments against government subsidies for wind power generation around the primary deficiencies of wind turbine technology: performance and return on investment (ROI).

It is obvious that any good investment must be made in worthwhile ventures that can show a reasonable return; and I believe it is fairly apparent that placement of wind turbine power generation technology in my home state of Ohio, vast areas of the eastern or mid-western United States, and indeed in most places in the continental United States, is not worthwhile.

Given the average annual wind speed limitations in most areas, and the relative inefficiency of wind turbines to transform wind into useful electrical power, the wind turbine technology we are subsidizing cannot produce enough electricity to be competitive with other more viable forms of generation, even when a generous allowance for future inflation of electricity costs is considered. The investment is being wasted; with no hope of a reasonable return, and without large subsidies from government entities to offset the investment losses and artificial increases in the cost of electricity, a viable business case for implementation of wind turbine power generation cannot be made.

To illustrate the economic shortcomings, I can point to specific high profile wind development projects I have analyzed in the past several months, including the Great Lakes Wind Energy Pilot Project in Ohio, the Highland Wind Farm expansion in Pennsylvania, and the Glacier Hills Wind Farm in Wisconsin.

The pertinent pieces of information required for the analyses are the power curves for the specific wind turbines, information regarding annual wind speed at the approximate elevations at the sites, and estimates of uptime and operation and maintenance (O&M) costs. This information seems simple enough, but is often difficult to gather because reports are often incomplete and conflicting with regard to economic details (begging the question, “Why?”).

Also, to apply a value to the electricity produced, I have characteristically used an approximation of the average wholesale price of electricity, which has been around $50/MWh for 2009-2010, and has been fairly consistent on an annual weighted average basis throughout the continental United States. It may be noted that the wholesale price of electricity varies widely on a daily basis depending on supply and demand, and also that certain forms of production are inherently more costly.

For example, Open Cycle Gas Turbine (OCGT) production is specifically designed to be fast reacting to peaks in demand and electricity generated in this manner can be sold for greater than $100/MWh when in demand. It makes sense to me, however, to use the average everyday wholesale price when analyzing the business case for a production system that is being touted as able to produce average everyday energy needs and to displace conventional average everyday production sources.  It would not make sense to evaluate wind turbines based on a cost comparison to a fast reacting OCGT system which is designed to be responsive to peaks in demand; wind turbines could never serve in this capacity.

Once the basic simple information is obtained, the analyses for these projects are fairly straight forward, and the details are presented in the attached charts and figures in the Technical Appendix. In all three cases, it is quite apparent that the wind turbines cannot produce enough electricity to return the investment and pay the annual operating and maintenance costs.

Considerations Not Included

Other points that should be made to further the arguments are [not included are the costs of required additional transmission facilities]:

  • These economic analyses do not account for the cost that will be incurred to maintain and operate a traditional back-up system for generating power when the wind is not blowing adequately, and for the added cost and inefficiency of cycling this back-up system on and off to balance the supply load against the variability of the wind generated power.
  • These analyses are presented for a 20 year period, although it is becoming evident that the useful life of many wind turbines is more like 10 to 15 years (see here and here). This can be contrasted to conventional power generation facilities which will remain productive for 40 to 60 years.
  • Any supposed reductions in dependency on conventional power generation, and any reductions in associated levels of pollution, attributed to use of wind power generation are highly suspect; because of the need to maintain and operate the back-up systems in an inefficient manner (see here and here).
  • The lowest wind conditions and the lowest power output will occur in the summer, when the electricity demand is highest.
  • Given the considerations above and the available theoretical power densities at the sites, the turbines will only convert a small fraction of the theoretically available energy passing by their blades. Assuming that as yet unknown and quite miraculous technology improvements implemented in the future are somehow able to double the turbine efficiencies, wondrously without increasing investment or O&M costs; these projects still do not present a truly acceptable business case or ROI.
  • Despite their supposed presentation as power sources for average everyday power needs, the wind turbine projects are often granted special Power Purchasing Agreements (PPAs) which allow prices for their electricity that are many times higher than average wholesale price. It is disconcerting that a large portion of the feasibility studies and the on-going discussion are often devoted to proposals to make the projects appear viable with public spending and it is evident that, to make these projects work, massive government subsidies and large increases in the cost paid for electricity will be required to offset the investment losses and attract investors.

Cape Wind Project

As another example of poor economic performance, the largest loser I have reviewed to-date is the massive Cape Wind Project in Massachusetts. The pertinent information regarding the specific wind turbines to be employed is difficult to come by (again the question, “Why?”) and my analysis is not as detailed; however, from published information the Cape Wind Project is supposed to produce three-quarters of the 230 MW power demand of the Cape and islands, which means a real average output of 172.5 MW, or about 41% of the rated 420 MW capacity.

Applying a generous assumption of 85% uptime means the turbines will operate 7446 hours per year; giving us 172.5 MW x 7446 hours = 1284 GWh/year. This estimate is actually more-or-less confirmed, within about 11%, on the Cape Wind website itself; which currently offers an updating display indicating that about 11,588,000 MWh of energy could have been produced since wind monitoring commenced. This seems like an impressive number until you divide it by the 8+ years of monitoring, and you get 1449 GWh/year.

Considering the annual average wholesale value of electricity in Massachusetts is also about $50/MWh per the DOE EIA, the annual energy generated by Cape Wind will be worth about $70 million per year; and subtracting annual operating and maintenance costs may leave about $50 million per year of this revenue. Again, this sounds impressive, until it is compared to the $2 billion that the project is expected to cost.

Even if a generous inflation rate is applied to the cost of electricity, the cash flow will not even come close to a return of this investment in the life of the wind turbines; unless someone deliberately raises the cost we pay for electricity. Unfortunately, this is already happening because a New England based utility company, National Grid, has already agreed to pay $207/MWh (4 times the current wholesale price) beginning in 2013 for half the power produced by Cape Wind.  National Grid is doing this to comply with a state law forcing them to purchase a certain amount of power from “renewable energy” sources, and the deal is considered critical to attract investors.

Exclusion of Other Ventures

Other than the harm to the national economy of the waste itself, the real problem with expending resources subsidizing non-viable wind turbine projects is that this inadvertently (or advertently) diverts resources from other efforts to improve our energy production strategy.

Because of recent events, we are hearing quite a few emotional comments regarding the need to reduce U.S. dependence on oil; and the recent tragic spill in the Gulf of Mexico is being used to justify investment in wind energy projects. However, it is reasonable to point out that oil is used to generate about 1% of the total electricity used in the USA, and one can effectively say that oil has nothing to do with the generation of electricity. Unfortunately, by increasing the cost of electricity, it is likely that we will make it more difficult to transition away from oil given that this fossil fuel is used for home heating and gasoline powered automobiles.

Also, in the rush to promote wind generation, development and improvement of other more viable means of energy generation are being ignored.  Instead of diverting resources to prop up wind projects we could be improving natural gas, nuclear, and coal generation.  We could also be improving the distribution system (grid) to reduce losses and improve reliability. Further, by subsidizing and offsetting the current deficiencies of wind generation, we take away the incentive to make the necessary improvements that might make it viable in some cases in the future.

Job Creation: The Green Myth

Tying back to point (3) regarding job creation and going beyond the specific arguments regarding the performance of the wind turbines themselves, I will point out that proponents for subsidized implementation of wind turbine power generation believe that this activity will create “green jobs.” I contend, however, that creation of jobs by subsidizing ventures that do not provide a viable return cannot work, and job creation cannot be a justifiable end unto itself.

This is simply an extension of the points I have made in the preceding paragraphs, and I will use an old tried-and-true analogy to make my point. If we wanted to simply create jobs, we could employ people to dig holes in the ground for no particular reason, and then employ other people to fill those holes in. By purchasing large earthmoving equipment, we could dig really big holes really fast, and stimulate employment at the manufacturing companies that make the earthmoving equipment and their steel and component suppliers.

Now, if we dig holes in both Ohio and Wisconsin, we could transport the dirt from Ohio to fill in the holes in Wisconsin, and conversely transport the dirt from Wisconsin to fill in the holes in Ohio. This would stimulate employment in the transportation industry for truck drivers and for truck manufacturers. The wear and tear on the roadways would also stimulate the need for road maintenance workers and all their equipment.

The analogy is facetious and I apologize for digressing into the absurd; however, I believe it illustrates my point that making jobs by subsidizing non-viable ventures cannot be an effective strategy.

Back to Economics

Keeping in mind the three principles that good investments must be made in viable worthwhile technologies, that we will be risking detrimental effects on ventures that are not being subsidized, and that job creation cannot be an end unto itself; it seems we need to coordinate the arguments against subsidies for wind power generation about the economic analysis. These are the easiest arguments to understand, and I believe these arguments will hit home for the majority of people. Other more in-depth technical analysis and subjective arguments will always be valuable and must be developed and presented as well; however, by keeping our eye on the economic ball, and clearly educating the investors and the public about the primary economic and performance deficiencies of wind power generation, we may be able to succeed in correcting the course of public opinion on this issue.

The basic economic analysis of the aforementioned Great Lakes Wind Energy Pilot Project in Ohio, Highland Wind Farm expansion in Pennsylvania, and Glacier Hills Wind Farm in Wisconsin are provided in detail in the next section. As previously indicated, with revenues based on realistic wholesale electricity costs, the cash flow analyses demonstrate that these projects will not break even within the projected 20 year period.

———

Jerry Graf has held engineering positions in industry for the last 27 years. The holder of Bachelor of Science and Master of Science degrees in Mechanical Engineering from the University of Akron, Mr. Graf is a founding member of the Mechanical Engineering Advisory Council at the University, and currently serves as the Council’s Vice-Chairman. His current interest is studying the technical aspects of wind power.

Technical Appendix: Details of the Economic Analysis

Graf Table 1


Graf Table 2

Follow this link to see Cash Flow Analyses

————————-

The following are links to other MasterResource essays on economic issues:

Windpower: Response to a Comment (on 4 cent/kWh wind and interfuel subsidies)

Heritage Foundation Windpower Study: Response to Center for American Progress

Rare Earth and Lithium Supplies Cloud Renewables

U.S. Wind Industry: Turbine Construction Won’t be Domestic

Federal and New York Officials Reward Spain’s Iberdrola at the Expense of the U.S. Taxpayers, Job Seekers, and Electric Customers

9 Comments


  1. Citizen++  

    Looks to me like your analysis fails to comprehend the inefficiencies in your economic system rather than the inefficiencies of the wind technology.

    Reply

  2. Jon Boone  

    There is much to admire about this essay. By any objective measure, industrial wind technology cannot succeed as a source of energy on its own merits. Its power performance is inimical to modern standards and its mode of energy delivery destabilizes the essential match between supply and demand, for whatever it generates is highly variable, minute-by-minute. However, if one evaluates industrial wind technology NOT as a source of energy but rather as a mechanism for delivering significant income mostly through tax avoidance, it may be nonpareil–particularly for CFO’s of multinational energy corporations with a lot of taxable income.

    Glenn Schleede has written a number of informative essays documenting how this is achieved–through federal production tax credits (that currently generate 2.2 cents for every kWh sent to the grid, with no indexing for CO2 reduction or fossil fuel saved); through incredibly generous federal double declining capital depreciation schedules, which allow the capital costs of wind projects to be fully recovered in as little as three years, depending upon the mode of financing; through a variety of state renewable portfolio standards laws in about 30 states presently (with national laws pending), requiring the state to purchase wind generation, even at irrational prices; and various state and local tax giveaways.

    According to the Palm Beach Post, Florida Power & Light Energy, a subsidiary of Florida Power & Light Co, the nation’s third largest utility and the owner of the nation’s largest stock of wind projects, claimed its quarterly earnings would surpass its parent company by 2012. I quote from that article: “FPL Energy boasted a 2006 profit of $610 million, triple its earnings in 2005. That followed an earnings increase of 200 percent between 1998 and 2002, then significant profit growth each year thereafter, mostly fueled by wind power projects.” General Electric, the one of the world’s largest producers and distributors of wind equipment and the company which bought up Enron’s wind plants in 2001, paid no federal income tax last year, despite having revenues in the billions.

    It is no accident that corporations like these, as well as BP, AES, and Sieman’s, either have purchased wind projects outright or entered into “equity partnerships” with them. In addition to the lucrative tax sheltering, these companies then market wind for its unearned environmental cachet. And of course, many buy the notorious green tags, in the process avoiding cleaning up their dirtiest burning coal facilities, reaping even more income.

    Mr. Graf does his analysis no favors by accepting the assumptions of Cape Wind operatives in order to move the discussion along. The lack of veridical information about wind performance deserves more than a few winking parenthetical asides. The evident collusion among regulatory agencies (and here I include FERC), grid officials, and wind LLCs to keep wind performance proprietarily confidential–despite the huge public subsidies that enable it–is nothing short of scandalous. All to keep politicians happy. No one should accept any claim made by a wind LLC without verifiable evidence, not even Jerry Graf.

    Reply

  3. John Droz  

    Jerry has done a good job here, but could easily have gone considerbly farther in several directions.

    For instance, regarding economic benefits, most of the “Green Jobs” speculation is based on a computer model called JEDI.

    The JEDI computer model is used to guess at the local financial benefits that may possibly result from constructing a wind project — but it has several favorable assumptions built into it, plus it ignores many negative economic consequences of renewable implementation

    Example: essentially all of the positive assumptions are exaggerated…
    — e.g. if the project buys a million dollars of steel from a local wholesaler, the community is credited with a million dollars of benefits. The reality is that the only local benefit is the markup by the wholesaler (5%±). It is through such grossly biased assumptions that the benefits are wildly exaggerated.

    Example: there are basically no negative assumptions made…
    — e.g. a farmer who signs up to lease several turbines may well cease farming operations, which means a loss to local suppliers (equipment, seed, fertilizer), loss of local employment, less food available (= higher $) for consumers, etc.

    To get a better idea of JEDI’s limitations and omissions read this critique by an independent energy expert: <>.

    And there are additional JEDI limitations that have come to the surface since his report was released!

    An an example, there have been numerous independent studies that have challenged the “green jobs” political assertions made by promoters of renewable energies. (None of these considerations are adequately dealt with by JEDI.) Here is a small sample:
    1 -<>
    2 -<>
    3 -<>
    4 -<>
    5 -<>
    6 -<>
    7 -<>
    8 -<>

    When taking this all into account, the general economic benefits to communities is likely to be ZERO. (Some contend that it is negative.)

    Reply

  4. John Droz  

    Sorry, none of the links came through, so I am reposting them differently.

    Jerry has done a good job here, but could easily have gone considerbly farther in several directions.

    For instance, regarding economic benefits, most of the “Green Jobs” speculation is based on a computer model called JEDI.

    The JEDI computer model is used to guess at the local financial benefits that may possibly result from constructing a wind project — but it has several favorable assumptions built into it, plus it ignores many negative economic consequences of renewable implementation

    Example: essentially all of the positive assumptions are exaggerated…
    — e.g. if the project buys a million dollars of steel from a local wholesaler, the community is credited with a million dollars of benefits. The reality is that the only local benefit is the markup by the wholesaler (5%±). It is through such grossly biased assumptions that the benefits are wildly exaggerated.

    Example: there are basically no negative assumptions made…
    — e.g. a farmer who signs up to lease several turbines may well cease farming operations, which means a loss to local suppliers (equipment, seed, fertilizer), loss of local employment, less food available (= higher $) for consumers, etc.

    To get a better idea of JEDI’s limitations and omissions read this critique by an independent energy expert: “http://tinyurl.com/mwdfse”.

    And there are additional JEDI limitations that have come to the surface since his report was released!

    An an example, there have been numerous independent studies that have challenged the “green jobs” political assertions made by promoters of renewable energies. (None of these considerations are adequately dealt with by JEDI.) Here is a small sample:
    1 -“http://tinyurl.com/cpmwrj”
    2 -“http://tinyurl.com/34q66kj”
    3 -“http://tinyurl.com/dhlvm5”
    4 -“http://tinyurl.com/lt9ero”
    5 -“http://tinyurl.com/3y5nggk”
    6 -“http://tinyurl.com/cl2hpf”
    7 -“http://tinyurl.com/2bdcbfk”
    8 -“http://tinyurl.com/cdjy7w”

    When taking this all into account, the general economic benefits to communities is likely to be ZERO. (Some contend that it is negative.)

    Reply

  5. David Bergeron  

    Great article. It seems to me that there is net job destruction (reduced national output) from subsidizing non-viable activities. The hole digging example is the extreme case, but a good case to consider. Say a country has 1 million workers and produces X amount of output. Then the government decides to force 10% of the laborers to dig holes. The country’s output of useful product will drop by 10%. The 100K government created jobs did not create 100K jobs, it destroyed the output of 100K workers. And we are worse off, not neutral. We all now share in the new 0.9X output. Prices adjust and we can now afford 10% less of everything.

    When we read about a renewable energy subsidy as creating 10,000 jobs, it is probably more accurate to say it “idled” 10,000 workers, and community output (and purchasing power) was reduced. Of course, to the extent that the activity has some benefit, less than 10,000 equivalent workers were idled. It also seems to me that if the activity had full market return, then total output is not changed and the policy did no damage.

    Reply

  6. Sarattus  

    While I am impressed with this analysis there is one thing no one seems to take into account. While we shut down or restrict energy production demand for energy will continue to grow. The new alternate wonders will have to match the present demand and provide for the future. If we impede it, serious damage and upheaval will ensue. Nifty trick eh? While we wait for the great Obama miracle to unfold, what are we to do? I believe in the theory that revolutions occur because a government is tyrannical or undemocratic. they revolt because a government is incompetent.

    Reply

  7. Cooler Heads Digest 18 June 2010 | GlobalWarming.org  

    […] The Primary Problems with Wind Power Jerry Graf, MasterResource.org, 17 June 2010 […]

    Reply

  8. Blowin’ in the wind | Tertium Quids  

    […] to develop wind power off the coats and otherwise toss subsidies at “green energy”, this piece on just how economically inefficient such efforts are makes for timely reading. Snip: Given the average annual wind speed limitations in most areas, and […]

    Reply