Understanding the Limits of Wind Power: Key Industry Terms

Two characteristics of industrial wind power crucially inform the public policy debate.

First, wind turbines have little or no “capacity value”; i.e., they are unlikely to be producing electricity at the time of peak electricity demand. Therefore, wind turbines cannot substitute for conventional generating capacity responsible for providing reliable electricity to customers.

Second, a kilowatt-hour (kWh) of electricity from wind has less value than a kWh of electricity from a reliable (“dispatchable”) generating unit; i.e., from a unit that can be called upon to produce electricity whenever the electricity is needed by electric customers.

These issues are important because “wind farm” developers and lobbyists have misled the public, media and government officials by making false claims and by using terms intended to confuse their listeners.

To address this problem, this post explains a few key electric industry terms that are important in understanding the critically important differences between the quality and value of

(i) the high cost, intermittent, volatile and unreliable electricity produced by wind turbines and

(ii) the lower cost, reliable and more valuable electricity produced by generating units that can be called upon to produce electricity whenever it is needed by electric customers.

Failure to understand the terms has led to faulty decisions by government officials and misunderstanding and incorrect reporting by media officials.

1. Generating Capacity

Generating capacity, measured in kilowatts (kW) or megawatts (MW), is a unit’s ability to produce electricity at an instant in time. This term can be confusing because there are two very different measures of generating capacity:

1. Nameplate capacity, which is the capacity rating shown on the nameplate attached to the generator by the manufacturer. (“Rated capacity” is often used synonymously with “nameplate capacity.”)
2. Summer capacity and winter capacity, which for many units (e.g., fossil-fueled) are often different from nameplate capacity because the unit’s ability to produce is affected by air temperature.

2. Capacity Value

Capacity value is also measured in kW or MW. Generating companies and grid managers must know the amount of generating capacity that can be counted on to help meet peak electricity demand since electricity cannot be economically stored and released. For many reasons, capacity value differs from generating capacity. Generally, this number is determined empirically; i.e., with a specific test of what the unit can produce (again in kW or MW) under specific test conditions.

3. Wind Turbine “Capacity Value”

In fact, the true capacity value of a wind turbine is the kW or MW of generating capacity that is available at the actual time of peak electricity demand on the electric grid serving the area. The true capacity value of a wind turbine or “wind farm” is generally less than 10% of nameplate capacity and often 0% or slightly above — simply because, at the time of peak electricity demand, the wind isn’t blowing at a speed that will permit the turbine to produce any or much electricity. Claims of wind turbine capacity value have been exaggerated by wind industry officials and lobbyists, by regulatory agencies, ISOs, RTOs (1), other grid manager’s arbitrary decisions (2).

4. Capacity Value for Reliable (“Dispatchable”) Generating Units

Capacity value for reliable (“dispatchable”) generating units– i.e., those designed to be available whenever called upon — may be less than their “nameplate” (or “summer” or “winter”) capacity for a variety of reasons. For example, they may have mechanical problems that prevent them from running at full rated capacity but which problems are not serious enough to take them out of service for repair or overhaul.

Grid managers often require that generating unit owners/operators report each day (e.g., around noon) how much capacity can be counted on during the next day from each generating unit.

5. Availability

The wind industry often tries to mislead people with this term. Generally, it means that a unit is physically available and has fuel needed to permit it to generate electricity when needed. Or, put another way, it is NOT out of commission (“off line”) for maintenance, repair or overhaul. Wind industry spokespersons often misuse this term by ignoring the critical second criterion; i.e. “has the fuel” (wind) needed to permit it to generate electricity. A wind turbine without wind has no real value to electric customers.

6. Generation

Generation is measured in kilowatt-hours (kWh) or megawatt-hours (MWh). This is an after-the-fact measure of the amount of electricity produced over some period of time (hour, day, week, month, year, etc.) Most reports by the US Energy Information Administration (EIA) show “net” generation — which is usually measured at a substation entry point to a transmission line. The term “net” reflects the fact that some of the electricity produced by a generating unit is used to power the generating unit itself (lights, pumps, scrubbers, precipitators, etc.).

7. Capacity Factor

Capacity factor is measured as a percentage of nameplate capacity. It is an after the fact measure with the percentage determined by dividing the actual (metered) output (in kWh or MWh), divided by the nameplate capacity (in kW or MW) times the number of hours in the period for which the calculation is done (e.g., 8,760 for a year).

8. Wind Turbine Capacity Factors

Wind turbines have low capacity factors because they are dependent on wind speed. They start producing a small amount of electricity with a wind speed about 6 or 7 miles per hour (mph), reach “rated” capacity around 31 mph and cut out around 56 mph. Therefore, their output is inherently intermittent, volatile and unreliable. A 1 MW (1,000 kW) wind turbine that produces 2,190,000 kWh of electricity during a year has achieved a capacity factor of 25%. That is 2,190,000 kWh divided by 1,000 kW x 8,760 hours; or 2,190,000 divided by 8,760,000 = .25).

9. Dispatchable Unit Capacity Factors

Capacity factors for reliable or “dispatchable” generating units vary widely depending upon (i) the design and intended purpose of the unit (i.e., for baseload, intermediate or peak load service) and (ii) the plans and choices of the operator who is responsible for keeping the electric grid in balance (electricity supply & demand, voltage and frequency).

a. “Baseload” units (often powered by coal or nuclear energy that heat water to produce steam that spins the turbine that produces electricity) are designed to run all or most of the time and often have annual capacity factors in the 70% to 90% range. They tend to take longer to start up and bring to full generating capacity.

b. “Intermediate load” units are those that can be “ramped” up and down (i.e., output increased or decreased) more quickly than units designed for “baseload” service). Some “intermediate load” units will use steam turbines and some will use gas turbines and some will use both.

Often these units will be powered by natural gas and, much less often, oil. Their annual capacity factors vary widely, perhaps from percentages in the teens to percentages in the 50s or 60s.

c. “Peak load” units are those intended for use primarily when electricity demand is at high levels. Generally these units will use gas turbine technology or internal combustion engines, powered by natural gas or oil. They can be started up and shut down quickly. Their annual capacity factors will often be in the range of 3% to 7% because they are intended for use only when electricity demand is high.

Hydropower units (falling water turns the turbines) may be used for baseload, intermediate or peak load service – depending on the availability of water in the area. For example, hydropower units provide baseload power in the Pacific Northwest but are used only for peaking service in areas with fewer water resources. Hydropower units are used for “load leveling” (i.e., keeping electricity supply equal to demand) because their output can be controlled instantaneously.

Units powered by biomass (wood, etc.) or geothermal energy are considered “dispatchable” and may also be used in baseload or intermediate service in areas where these energy sources are available. As indicated above, wind turbines are “intermittent” and neither reliable nor dispatchable because they are dependent on wind speed.

Solar photovoltaic panels are also intermittent sources of electricity because they are dependent on sunlight.

10. Efficiency

This term is often used incorrectly; that is, when the correct term is “capacity factor.” Efficiency, as that term is used in the electric industry, refers to the relationship between BTU of energy input and kWh output. The result of this calculation is generally referred to a unit’s “heat rate.”

Postscript

An excellent article from Power-Gen Worldwide explains how fast starting gas-fired generating units are being built in the U.S. for the specific purpose of providing backup generation and grid balancing in areas where so-called “wind farms” (industrial wind parks) are built.  The article explains the differences between spinning reserve generating units; generating units that are on line and producing at less than full capacity; and units that are in “standby” that can be started up and begin producing in about 10 minutes.

Footnotes

(1) ISO = Independent System Operator; RTO = Regional Transmission Operator. Both types of organizations are involved in managing an electric grid.

(2) Capacity value was also exaggerated in a misleading report produced by GE in March 2005 for the New York State Energy R&D Authority (NYSERDA). That report was cited by the NY ISO to arbitrarily assign “wind farms” in New York a 10% capacity credit (i.e., 10% of nameplate capacity) during summers and 30% in winters – an action that has since been found to be unjustified.

4 comments

1 Joe Heater { 03.14.10 at 12:04 pm }

Glenn,

Let me point to a phrase that is often used in the media to describe wind power generating capacity that is very misleading ; “a wind farm has the capacity or ability to power X number of homes.” For example, in todays Chicago Tribune in an article titled, Wind trubines stir up ill will, the writer opines that, “Today 126 turbines dot the county, with another 19 just over the border in Lee County. They have been making enough electricity since December to power 55,000 homes, roughly twice the needs of Oak Park.”
See the entire articile here: http://www.chicagotribune.com/business/ct-biz-0314-wind-energy–20100314,0,3413539.story

Over the last several weeks there have been a number of days that wind velocity has been less than 7 mph so I rather doubt that the wind farm was powering Oak Park or any other community.

The number of homes definition of a wind farms capacity or generation capability needs to be challanged every time it’s used. You might want to consider adding the X homes phrase to your list. The proper definition might read something like this; The Blow Hard Wind farm can provide power for up to x amount of homes 25% of the time on an random basis.

Joe Heater
Palatine, IL

2 Pierre Desrochers { 03.14.10 at 8:15 pm }

But I’ve learned from Daniel Kammen that these problems magically disappear as you scale things up and that Germany proves that you industry types are prisoners of your old electrical engineer paradigm :)
http://www.youtube.com/watch?v=ynntdk6eGSY&feature=player_embedded#

3 Tim W. { 03.15.10 at 10:47 am }

I’d just like to say thank you, Glenn. In the Midwest, wind energy startups rise and fall at the drop of a hat. Scrambling to buy up land in the desired wind corridor with the expectation that another bigger fish will have to come along and deal with them at a premium. This whole wind farm idea doesn’t amount to much more than a Ponzi scheme where the uninformed taxpayer foots the bill for a federal boondoggle. I keep asking these farmers how does this huge eyesore make money when the wind doesn’t blow and all I ever get is the tired, “Well it has to make money otherwise they wouldn’t be doing it.” Ugh. Anything “makes” money as long as taxpayers subsidize it people.

4 Consumer Energy Alliance { 03.17.10 at 1:37 pm }

4. Inspite of some limitations with the wind power generation, there is still huge potential in this sector. It was a record year in 2009 as wind capacity in the United States saw substantial growth. As of December 31, 2009, wind capacity has grown to nearly 35,000 MW. That’s the equivalent of more than 9.7 million homes. The U.S. wind industry currently directly employs more than 2,000 people. Further development of wind resources as spelled out in the DOE’s plan for future wind capacity that will account for at least 20% electricity generation in the United States by the year 2030. In the beginning of 2010, the National Renewable Energy Laboratory released an update of wind energy potential in the United States listed at approximately 10.5 million MW of wind power, or almost nine times larger than current U.S. electricity consumption.
Want to learn more about balanced energy for America? Visit http://www.consumerenergyalliance.org to get involved, discover CEA’s mission and sign up for our informative newsletter.